International Arbitration

International Arbitration Information by Aceris Law LLC

  • International Arbitration Resources
  • Search Engine
  • Model Request for Arbitration
  • Model Answer to Request for Arbitration
  • Find International Arbitrators
  • Blog
  • Arbitration Laws
  • Arbitration Lawyers
You are here: Home / Construction Arbitration / NEC Contracts: Dispute Resolution Under NEC3 and NEC4

NEC Contracts: Dispute Resolution Under NEC3 and NEC4

02/11/2025 by International Arbitration

The NEC family of contracts, short for New Engineering Contract, is a suite of standard forms of contract published by the Institution of Civil Engineers (“ICE”). NEC is designed for construction, engineering, and infrastructure projects and is used widely in the UK public sector. Its use has also expanded globally, particularly in jurisdictions such as Hong Kong, Australia, New Zealand, and increasingly in countries like Ireland, Peru, and the UAE for complex, collaborative projects.

NEC contracts are designed to be jurisdiction-neutral and use plain English, making them suitable for use in any country and for any type of project where a collaborative and proactive management approach is desired.[1]

Dispute Resolution NEC3 And NEC4The practical objective and core idea behind NEC contracts are to move away from the traditional, adversarial culture of the construction industry and replace it with a collaborative, proactive, and risk-managed approach to project delivery.[2] The idea is to stimulate good project management by providing a clear, flexible, and simple contractual framework that encourages the parties to work together as a team, rather than as adversaries.[3]

This note explains what NEC is and where it is commonly used, summarises the NEC dispute ladder under NEC3 and NEC4, highlights the key NEC4 innovations that affect dispute avoidance and resolution, and provides practical, process-oriented guidance for parties already facing disputes on NEC contracts.

What Are NEC contracts?

NEC was developed by the Institution of Civil Engineers to respond to the adversarial patterns found in traditional construction contracts. The NEC philosophy rests on the following main pillars:

  • Flexibility: One of the principal goals was to make NEC contracts as flexible as possible, so they can be used in different scenarios and adapted to any or all of the traditional disciplines, and used in any country in the world.
  • Clarity and Simplicity: The contracts use plain English and short sentences so people on projects can understand their obligations without wading through legal jargon.
  • Encourage proper project management: NEC builds procedures into the contract that push the parties to plan, manage risk, and spot problems early, rather than waiting for issues to evolve into claims.
  • Promote co-operation: NEC expressly asks the parties to act in a spirit of mutual trust and co-operation, so everyone is meant to focus on dealing with problems rather than scoring tactical wins.[4]

These features make NEC attractive for public sector programmes and for major engineering projects where collaborative behaviours reduce project risk.

Most Common NEC Contract Forms

NEC is a suite rather than a single form. The forms most commonly encountered are:

  • Engineering and Construction Contract (ECC): This is the most popular NEC contract.[5] It is used for major construction and engineering projects, including infrastructure, buildings, process plants, and more, where both design and construction can be included within the scope. It is the core document from which various pricing options are selected.
  • Engineering and Construction Subcontract (ECS): This form is designed to be used “back-to-back” with a main ECC contract, for when the main contractor sub-lets part of the work to a subcontractor. It mirrors the structure and processes of the ECC to ensure consistency across the project.
  • Professional Services Contract (PSC): This contract is used for appointing consultants and service providers, such as architects, engineers, project managers, and quantity surveyors. It ensures a consistent management culture across the professional services part of a project that might be using an ECC for the main works.
  • Term Service Contract (TSC): Designed for maintenance, management, and facilities management work over a defined period, rather than new construction projects. This is commonly used for highway maintenance or building services.
  • Engineering and Construction Short Contract (ECSC): This is a simplified version of the ECC, intended for use on lower-risk, more straightforward projects that do not require the sophisticated management techniques of the full ECC form.
  • Design, Build and Operate Contract (DBOC): It is a specific form of the contract introduced in the NEC4 suite, designed to provide a single, integrated solution for clients who want one contractor to handle a project from initial design and construction through to a defined period of operation or maintenance.

Common Main Options (Payment/Pricing Mechanisms)

Within the main contracts (especially the ECC), users must select one of several “main options” which define the payment mechanism and risk allocation. The most common options are:

  • Option A – Priced contract with activity schedule: This is a lump-sum contract where the contractor is paid based on a pre-agreed activity schedule. It offers cost certainty for the client and is popular for well-defined projects.
  • Option B – Priced contract with Bill of Quantities (BoQ): Similar to Option A, but uses a bill of quantities for payment. The quantities are remeasured, but the rates are fixed.
  • Option C – Target contract with activity schedule: This is an “open-book” contract with a “target” price. The client and contractor share the pain or gain of the final cost against this target, encouraging a high degree of collaboration.
  • Option D – Target cost contract: Where the client and the contractor agree on an estimated price using a Bill of Quantities and then share any cost savings or overruns against that target, incentivizing collaborative financial management.
  • Option E – Cost reimbursable contract: The client pays the contractor’s actual defined costs plus a fee. This is often used for emergency work or projects with high scope uncertainty, where the client largely bears the financial risk.
  • Option F – Management contract: A management contract where the contractor manages various specialist subcontractors and is reimbursed for all actual subcontractor costs plus a set fee for their services, with the client bearing the primary financial risk for the project works.

The main difference between these options is the level of design definition and the appetite for financial risk. Options A and B offer cost certainty with higher contractor risk, while E and F shift most of the risk to the client for complex or undefined projects. These features let the employer and contractor pick the procurement route that fits the project.

Most Common NEC versions

The most common versions of the NEC contracts used in practice today are the NEC3 and the current iteration, NEC4:

  • NEC4 is the latest suite, published in June 2017, and represents the current industry standard, featuring improvements in clarity, flexibility, and new contract types like the Design, Build and Operate (DBOC) and Alliance Contracts (ALC). Public sector entities and new projects are increasingly adopting NEC4 as the default.
  • NEC3, published in 2005 and last fully revised in 2013, was the dominant version for over a decade and is still widely used for a large number of existing projects,[6] including major, long-term infrastructure schemes (such as Hinkley Point C in the UK) that will continue using it until completion.

While earlier versions like NEC and NEC2 are largely obsolete in new procurement, the transition between NEC3 and NEC4 is ongoing, meaning both are frequently encountered in the industry. The Engineering and Construction Contract (ECC) within these suites remains the most commonly used contract form.[7]

Judicial Interpretation of NEC Contracts

The interpretation of NEC3 clauses has been clarified through a series of court decisions that demonstrate the judiciary’s pragmatic approach to contract interpretation. For example, in RWE NPower Renewables Ltd v JN Bentley Ltd,[8] the UK courts held that NEC3 contracts should be construed as a whole, emphasising consistency and commercial common sense rather than technical literalism. Similarly, the Scottish Court of Session in SSE Generation Ltd v Hochtief Solutions AG addressed the contractor’s liability for defects and underscored that NEC provisions, such as Option M, are not guarantees of perfect performance but instead impose an obligation to exercise reasonable skill and care.[9] These decisions highlight how courts tend to uphold the collaborative intent and plain-English drafting of NEC rather than treat it as a purely prescriptive document.[10]

Dispute Resolution: NEC3 vs. NEC4

The dispute resolution process under NEC contracts is built to be quick, multi-tiered, and focused on solving problems before they escalate.[11] The exact steps depend on which “W” Option clause the parties select in the Contract Data. At its core, the NEC approach to dispute resolution is guided by a few key principles:

  • Dispute avoidance: The contract encourages proactive communication and early warnings, supported by the impartial role of the Project Manager, to resolve issues before they develop into formal disputes.
  • Adjudication first: Any formal dispute must first be referred to adjudication before moving on to arbitration or litigation. This ensures that issues are dealt with swiftly and project progress is not unnecessarily delayed.
  • Interim binding decisions: The adjudicator’s decision is binding in the meantime, and both parties must comply with it unless or until it is overturned by the final decision maker in arbitration or court proceedings.

The Dispute Resolution Options (W Clauses)

The Dispute Resolution Options (W Clauses) in NEC contracts give parties a choice of three paths in the Contract Data:

  • Option W1 applies mainly to international projects where the UK Housing Grants, Construction and Regeneration Act 1996 does not apply. It requires disputes to first go to senior representatives from each party for quick resolution attempts. If unresolved, adjudication follows, typically with a 28-day decision deadline. If dissatisfied, a party has four weeks to notify its intent to go to the final tribunal; otherwise, the adjudicator’s decision is final.
  • Option W2 is for UK projects where the statutory right to adjudication applies. Either party can start adjudication immediately, with the senior representative stage optional and not blocking the statutory right. The path after adjudication is the same as W1, with a four-week notice window for escalating to arbitration or court.
  • Option W3 is new and replaces adjudication with a standing Dispute Avoidance Board of experts that monitors the project and issues non-binding recommendations to prevent disputes. Only if a party is unhappy with these can the dispute go to the final tribunal within set time limits.

All options combine early engagement with a defined final forum, but W1 and W2 focus on adjudication as a fast interim step, while W3 emphasizes ongoing prevention through proactive monitoring.​

Final Stage: Arbitration or Litigation

If a party challenges the adjudicator’s decision (or, under Option W3, a DAB recommendation) within the specified timeframe, the dispute moves to the final stage of resolution, either arbitration or litigation, as chosen in the Contract Data.

The parties make this choice when the contract is formed, long before any dispute arises, by specifying their preferred forum and, in the case of arbitration, the applicable rules or institution.

Regardless of that choice, every dispute must first go through the mandatory step of adjudication under Options W1 or W2. Only after an adjudicator has issued a decision can a dissatisfied party take the matter to arbitration or court.

Arbitration is a common choice in international construction projects because it offers confidentiality, procedural flexibility, and the ability to appoint an arbitrator with specialist industry expertise, which traditional litigation rarely provides. For international projects, arbitration is almost always preferred, as awards are generally easier to enforce across borders under the Convention on the Recognition and Enforcement of Foreign Arbitral Awards than national court judgments.

Main Differences Between NEC3 and NEC4: Dispute Resolution

NEC4 shifts the emphasis from simply managing disputes to actively avoiding them, and it adds new, formalised tiers that sit before adjudication or final determination. The most important practical changes are set out below.

Senior Representative Negotiation (Options W1 and W2)

NEC4 introduced a new stage where senior representatives from each party meet to try to resolve disputes quickly. Under Option W1 (used where UK statutory adjudication does not apply), this step is a required part of the process. Under Option W2 (used where the Housing Grants, Construction and Regeneration Act 1996 applies), the senior representative stage is encouraged but not mandatory, since the Act allows either party to refer a dispute to adjudication at any time.

The idea is simple: give the parties a short, focused opportunity to resolve issues at a senior level before they escalate. Senior representatives are named in the Contract Data, and both sides must agree to refer a dispute to them. Each party then submits a brief statement of case, usually no longer than ten pages, within a week of notification. They meet over the following three weeks to try to find a solution.[12]

The process is deliberately quick and confidential, and anything discussed cannot be used later in adjudication or litigation. In practice, though, this stage can be demanding on major projects, as senior executives often have limited availability. While the step encourages collaboration, it can also be used tactically to delay formal proceedings if not managed carefully.[13]

Option W3: The Dispute Avoidance Board

NEC4 also introduced Option W3 for projects outside the UK where statutory adjudication does not apply. This option establishes a standing Dispute Avoidance Board (DAB), which monitors progress, visits the site, and helps resolve issues before they turn into disputes.

The DAB, usually made up of one or three members, is appointed under the NEC Dispute Resolution Service Contract. It meets regularly, reviews the project, and can issue non-binding recommendations within a few weeks of a potential dispute being raised. If a party disagrees, it has four weeks to issue a notice of dissatisfaction; otherwise, the recommendation becomes final.[14]

When used properly, the DAB can prevent many disputes from escalating to adjudication or arbitration, acting as a proactive “early warning” tool rather than a reactive dispute forum.

Early Warning Register

To make its purpose clearer, NEC4 renamed the Risk Register as the Early Warning Register. The change reinforces NEC’s goal of spotting and managing issues before they grow into formal disputes.

Clearer Procedures and Alignment

NEC4 also refined its dispute resolution procedures to make them more consistent and easier to administer. It clarified how adjudicators and DAB members are appointed, shortened the window for correcting clerical errors in adjudicators’ decisions, and improved the overall timing and structure of dispute processes. These updates aim to make dispute resolution more predictable and to help parties focus on solving problems through the contract rather than resorting to tactical manoeuvres.

Conclusion

NEC contracts provide a practical, management-focused framework built on clarity, collaboration, and early problem-solving. NEC4 strengthens these principles by adding clearer procedures, senior representative negotiations, and the Dispute Avoidance Board to prevent disputes before they escalate. Courts and practitioners regard NEC4 as a mature, well-structured evolution of NEC3 that promotes cooperation rather than confrontation. Ultimately, the success of any NEC contract depends less on its wording and more on disciplined, proactive administration by the parties involved.

  • Nina Jankovic, William Kirtley, Aceris Law LLC

[1]               NEC, Evolving to be the world’s favourite procurement suite.

[2]               ICE, New Engineering Contract (NEC).

[3]               M. Rowlinson, A Practical Guide to the NEC3 Engineering and Construction Contract (2011), Chapter 1.3.

[4]               M. Rowlinson, A Practical Guide to the NEC3 Engineering and Construction Contract (2011), Chapter 2.

[5]               M. Rowlinson, A Practical Guide to the NEC3 Engineering and Construction Contract (2011), Chapter 1.1.

[6]               Metroun, NEC Contracts Explained, 16 September 2020.

[7]               A Lamb Associates, NEC3 vs. NEC4 – What’s Changed.

[8]               RWE NPower Renewables Ltd v JN Bentley Ltd [2014] EWCA Civ 150, [2014] CILL 3488.

[9]               SSE Generation Ltd v Hochtief Solutions AG [2016] CSOH 177, 2017 GWD 3-39.

[10]             A. Yeu, NEC3 Case Law Review, in S. Brekoulakis (ed.), Arbitration: The International Journal of Arbitration, Mediation and Dispute Management (November 2018), pp. 347–360.

[11]             M. Rowlinson, A Practical Guide to the NEC3 Engineering and Construction Contract (2011), Chapter 19 (Dispute Resolution).

[12]             Weightmans, NEC4 Dispute Resolution Procedure, 26 April 2023.

[13]             Weightmans, NEC4 Dispute Resolution Procedure, 26 April 2023.

[14]             Mills & Reeve, NEC4 – What’s new in the resolution of disputes?, 28 April 2021.

Filed Under: Construction Arbitration

Search Arbitration Information

Lukoil Arbitration Cases

NEC Contracts: Dispute Resolution Under NEC3 and NEC4

Understanding Risk Allocation in FIDIC Construction Contracts

Provisional Measures in CAS Arbitration: IGF v. FIG

Errors in the Employer’s Requirements under FIDIC Contracts: Legal Implications and Lessons Learned

Managing Construction Disputes: Understanding the Causes

China’s New Arbitration Law 2025: Overview of Key Changes

Unpaid Invoices and International Arbitration: Is It Worth It?

AI Construction Arbitrator: Revolutionising the Future of International Arbitration?

Effective Case Management in International Arbitration

Analysing the Site Visit Model Protocol for International Arbitration

Interpreting Treaties in Investment Arbitration

© 2012-2025 · IA